Thompson County Park Phase II Programming: Pricing & Project Prioritization

Please Review the Project Pricing and Weigh in on Prioritization

After vetting the projects and their various components with the Core Team in December, they were priced by two independent cost estimators (except for the Land Bridge, Noise Mitigation, and Daylighted Stream components, which were priced by our engineering consultants, Kaskaskia and EOR). The Draft Programming Package below reflects the reconciled cost estimates for each project. Please review and weigh in on priority preferences by Friday the 26th. The selected projects will move forward to Schematic Design and materials will be prepared to aid in seeking additional funds for implementation.

File name:

-

File size:

-

Title:

-

Author:

-

Subject:

-

Keywords:

-

Creation Date:

-

Modification Date:

-

Creator:

-

PDF Producer:

-

PDF Version:

-

Page Count:

-

Page Size:

-

Fast Web View:

-

Choose an option Alt text (alternative text) helps when people can’t see the image or when it doesn’t load.
Aim for 1-2 sentences that describe the subject, setting, or actions.
This is used for ornamental images, like borders or watermarks.
Preparing document for printing…
0%

Click anywhere in the document to add a comment. Select a bubble to view comments.

Document is loading Loading Glossary…
Powered by Konveio
View all

Comments

Close

Add comment


I thought we were moving these diagrams to the back and only having the updated diagram in the body of the report?
0 replies
change to Thompson Park Center instead of Dakota Lodge
0 replies
separate into two words
0 replies
can we spell out this acronym the first time?
0 replies
What's going on here?
0 replies
Can we call out the specific study with the full title? Just wanting to be clear that we're building off previous work here
0 replies
Water quality investigation needs to be included in the SD of the stream daylighting. This might be able to be done in house, but if needed, we may need a third party to assist
0 replies
Need to confirm, but it sounds like this sentiment needs to go away - SSP is not interested in the regional park idea
0 replies
Suggestion
Do we want to specify that this building will have sewer/water capabilities and will be tempered? Want to make sure that the cost shown in the estimate has some context - the building shown as precedent looks simple (no heat, water, sewer)
0 replies
Suggestion
May be helpful to have the images keyed to the map.
0 replies
Suggestion
Not sure how the daylighted stream adds to stormwater storage.
0 replies